Bloor Street Construction June Update

North east sidewalk starting soon. Havelock step to go. New trees in progress.Street tree planting in progress

By this weekend work should be completed on the south sidewalk and base asphalt from Montrose Ave. to Havelock St. Work will then be moving to the remaining north sidewalk at Bartlett Ave. headed east towards Montrose Ave. Expect noise, dust and sidewalk closures as excavation and reconstruction take place. Sorry for the inconvenience.

As part of this project we will be re-grading the Havelock St. and Bloor St. intersection to remove the legacy two-step curb and ramp on the north side.

Get a last look at the two-step curb at the top of Havelock St.

Get a last look at the two-step curb at the top of Havelock St. – to be replaced with a normal one-step curb and pedestrian curb cut.

Tree planting started on June 9, on the south side. City Forestry Operations is planting 

approximately 10 trees a day. The species are Maple, Elm and Locust. You can learn more about the improved growing conditions for boulevard trees being provided on Bloor in this recent CBC news report.

Concord Avenue south of Bloor is closed this week as the new sidewalk “bump out” is installed. Further planting and streetscape upgrades will be completed there in the fall.

All major road and sidewalk work between Lansdowne Ave. and Havelock St. should be completed by the end of June. The area east of Havelock St. will be completed by the end of July.

Additional streetscape upgrades will be completed in the fall.

Thanks again for your patience and cooperation.